Obtaining electricity connection for your business

​​


Step 1: Get approval to purchase meter and do external works


A registered electrical contractor submits new application via OneBiz online system.

Documents required:

  • Complete Permit to Dig application (Form G) with attached plan and picture
  • Valid worker pass
  • Development approval letter
  • As Built Single Line Diagram by electrical contractor

Upon completed application, DES will issue letter of approval to purchase meter and approval to proceed with excavation work along with Form I (Permit To Dig approval) whereby applicant can simply download the approval letters via OneBiz.


Step 2: Excavation works done by contractor


After obtaining approval letters and purchasing of meter from the approved vendor, excavation and underlying works can be done immediately by appointed licensed electrical contractor.

Meter installation and arrange testing by Professional Engineer can also be done at the same time.


Step 3: Get approval for permanent electrical connection


Payment of connection charges can be made immediately after the completion of excavation works via online at OneBiz or cash at D&T Building at Anggerek Desa.

The applicant will received approval for permanent supply via OneBiz system after payment is made and after electrical contractor submits certification of test report by a Professional Engineer, and other relevant documents.

Documents required:

  • Form DCS-009
  • Occupational Permit
  • Receipt, invoice of purchase of meter
  • *Confirmation letter of testing with report on Electrical installation and approved single-line diagram by Professional Engineers
*Professional Engineers have to use the  BS7671 Test Forms and attached them with their testing certification letter